For over 35 years this Cummins diesel has been there when the city and residents of this town on the Hudson needed. It didn’t even need to be replaced but when the city was offered a new 1 MW without having to pay who wouldn’t take a new shiny toy.
PROJECT DETAILS
Categories: | |
Client: | Beacon Water Treatment Plant |
Location: | Beacon NY |
Completed: | 2015 |
Value: | 10000 |
WHAT HAPPENED
15,000 lbs.
30 feet + 130 miles
- Disconnect from existing lines (fuel, exhaust, water,.
- Maneuver inside around existing equipment and stairs to double glass door
- No loading dock or machine access. No damage allowed!
- Exit building through standard glass doors and 4 concrete steps and pad
- Wrecker Crane loading onto flatbed trailer
- 3 Hour Highway Transport